A delayed software project ends early: Triple Point v PTT
When a delayed project is terminated, agreed delay damages and general damages may cover different periods. Triple Point v PTT shows why milestone records, termination notices and liability caps need to be reviewed together before asserting a project claim.
The unfinished project problem
A software rollout misses milestones and the customer ends the contract. The supplier says that an agreed delay payment applies only to work eventually completed. The customer counts every day of delay and replacement costs. Before comparing those positions, identify what the contract says about each period and each type of loss.
What Triple Point decided
Triple Point Technology Inc v PTT Public Company Ltd [2021] UKSC 29 concerned a software project, delay damages and a liability cap. The Supreme Court rejected an approach that excluded agreed delay damages merely because the contractor had not completed the work before termination. On the contractual wording, such damages operated up to termination, with general damages potentially relevant afterwards. The court also addressed the cap and its exceptions, including the meaning of negligence. Its conclusions depended on construction of the actual clauses. Read the official judgment.
This is not a general entitlement to stack every contractual remedy or to recover the same loss twice.
Organise the project evidence by milestone
Create a table of deliverables, contractual dates, approved extensions and actual acceptance. Keep the definitions of completion and acceptance beside the table. Distinguish a demonstration, test environment release and production acceptance; treating them all as “delivery” can obscure the central issue.
Preserve change requests, dependency logs and records of customer access or data provision. A programme may show a missed date without explaining responsibility. Include both sides' progress reports and unresolved objections, rather than only the documents supporting your preferred account.
Collect the termination notice, its method of delivery and the clause relied on. Record what work remained and what the parties did immediately afterwards. Replacement supplier proposals should identify whether they complete the original scope, fix defects or introduce new features. Keep those categories separate when calculating additional cost.
Prepare a remedy worksheet showing the claimed delay period, daily or weekly calculation, cap and any contractual exception relied on. Mark general damages separately from agreed delay damages, and record payments or credits already received. Bring the entire limitation clause; one sentence may depend on definitions elsewhere.
A common misreading
“Termination cancels the delay clause” is too simple. So is “the daily rate runs until a replacement finishes”. The contractual allocation of pre-termination and post-termination losses requires careful reading. A reference to negligence in a negotiated business contract also cannot safely be understood from its everyday meaning alone.
Before sending a quantified demand
Ask whether the contract was validly terminated, what notice steps were required and which losses fall within any cap. Discuss disputed extensions and possible double counting. If your priority is obtaining usable code or project materials, say so: that practical objective may require attention alongside a money claim.
The decision was delivered in 2021 and does not resolve every technology contract. LegalPath can help you browse public cases and lawyer profiles, while your milestone history and signed terms provide the starting point for advice.