Work started before signature: RTS Flexible Systems v Müller
Starting work while a contract is still unsigned can leave the parties arguing over both formation and terms. RTS Flexible Systems v Müller explains why negotiations, conduct and project records should be examined together rather than relying only on signature status.
The project did not wait for the paperwork
A letter of intent expires, negotiations continue and work carries on. Months later, a dispute arises about price, delay or responsibility. One side points to an unsigned document; the other points to completed performance. The legal question is not answered by choosing whichever fact seems more convenient.
What the Supreme Court found
RTS Flexible Systems Ltd v Molkerei Alois Müller GmbH [2010] UKSC 14 concerned work performed while the parties negotiated a fuller agreement. The Supreme Court held that a binding contract had been reached on the terms identified in its judgment, notwithstanding an unfulfilled signature provision. The parties' objectively assessed words and conduct supported the conclusion that the subject-to-contract requirement had been waived in those circumstances. The case does not abolish such provisions. Read the official judgment, particularly paragraphs 45–55 and 85–89.
The practical problem is proving the bargain actually reached, including its limits, rather than assuming performance supplies every missing term.
Build a version history
Gather the letter of intent, extensions, drafts, tracked changes and final negotiation emails. Record who circulated each version and which issues remained open. An attachment's filename is not reliable proof that it became the agreed contract. Preserve the message carrying it and any response accepting or rejecting terms.
Make a separate performance timeline: authorisation to start, purchase orders, deliveries, site access, milestone payments and acceptance. Identify references to particular terms in those records. If staff performed work because they believed temporary authority existed, preserve that explanation rather than assuming the commercial team held the same understanding.
List all disputed terms, not merely whether there was “a contract”. Price, scope, liability, acceptance and delay may each require analysis. Note which matters were agreed orally, which were recorded in writing and which were never discussed. Bring evidence of authority where someone purported to commit a company.
Explain payments and benefits already received. Mark whether an invoice was paid against a purchase order, under a letter of intent or without an explanation. If work stopped, preserve the reason given at the time. These details help an adviser distinguish an enforceable agreement from a possible claim concerning work supplied without one.
Two unreliable assumptions
An unsigned draft is not automatically binding because work began. Equally, lack of signature does not automatically mean that no obligations exist. A provision requiring execution deserves serious attention, but its effect must be assessed alongside the evidence and relevant law. This judgment's finding of waiver was a conclusion on its particular record.
What to ask next
Ask when an agreement may have formed, which terms can be proved and whether different project phases had different legal foundations. Discuss how to document continuing work while the issue is resolved. Avoid issuing a confident termination notice before understanding the obligations you might already have assumed.
This article reviews the 2010 decision and is not a current-law opinion on your documents. Use LegalPath to browse public cases and lawyer profiles, then take a complete version history to the consultation.