A cancelled delivery and no substantial damages: Bunge v Nidera

An early cancellation can breach a supply contract without producing the damages a buyer expects. Bunge v Nidera explains why the delivery window, later events and the actual loss need separate attention when preparing a commercial dispute.

Jurisdiction: England and Wales

The question behind a cancelled order

A supplier says that an external restriction makes delivery impossible. The buyer treats that message as a breach and starts calculating the difference between the contract price and a higher market price. Those calculations may be useful, but they do not answer every question. Before discussing a damages figure, a lawyer needs to understand what performance would actually have been worth.

What the court decided

In Bunge SA v Nidera BV [2015] UKSC 43, a wheat contract contained GAFTA prohibition and default provisions. The seller cancelled prematurely after an export embargo was announced. The embargo subsequently prevented delivery during the contractual shipment period. The Supreme Court allowed the seller's appeal on damages and substituted nominal damages of US$5 for the substantial award. The default clause did not exclude the compensatory principle applied in the case. The seller's early cancellation remained wrongful; the damages conclusion was a separate issue. Read the official judgment, particularly paragraphs 23–36.

This is a review of that 2015 decision, rather than advice about any current embargo, sanctions regime or version of a trade association form.

Build two timelines before a consultation

Prepare one timeline of communications: the order, acceptance, delivery notices, cancellation and response. Prepare another of external events: when a restriction was announced, when it started, whether it changed and when delivery would have occurred. Keeping them separate helps distinguish information available at the time from facts learned later.

Bring the complete contract and the actual edition of any incorporated standard conditions. A clause copied from a current website may differ from the version governing an older transaction. Include amendments, quantity options and notices narrowing a delivery window. These details can change the counterfactual against which a loss is assessed.

Create a loss schedule with a document beside every entry. Identify replacement purchases, extra transport, storage, refunded payments and any costs saved. Label a quotation as a quotation, rather than treating it as a completed substitute transaction. Preserve the reasons for accepting or rejecting alternatives, including availability, quality and financing constraints.

A common misunderstanding

A finding of breach does not automatically establish the amount claimed. Equally, a small award in this case does not mean a supplier can cancel at will whenever performance looks difficult. Whether cancellation is permitted, whether a restriction genuinely affects the promised goods, and whether reasonable alternatives existed require their own analysis. Do not assume another contract's default formula has the same meaning.

Questions worth taking to a lawyer

Ask which obligations would have survived without the cancellation, what evidence shows the likely outcome, and which claimed costs were caused by the breach itself. Explain whether your priority is replacement supply, repayment or compensation; each objective may require different immediate steps. Keep originals and avoid rewriting historical explanations after a dispute develops.